2019
NUOVA LINATE - AMPLIAMENTO CITY AIRPORT DI MILANO
Ampliamento e revamping Aeroporto “Enrico Forlanini” di Milano Linate
Progetto Preliminare, definitivo, esecutivo (Nuova Facciata)
P. Fattibilità e Preliminare opere civili, strutture, MEP (Corpo F e Corpo BNCN)
Progetto preliminare e definitivo interior design (Aerostazione Arrivi)
Committente
SEA SpA
Tipologia di intervento
Costruzione & Revamping
Destinazione d'uso
SERVICES, AIRPORTS
Valore dei Lavori
40 Million € (Full project)
7.5 Million € (Expansion)
Luogo
MILANO
Periodo
2016-2018
Concept Design
Studio Cerri & Associati (New Façade design)
SEA Spa (Art Direction)
TEKNE Spa (Expansion, revamping and interior design)
Numeri
Nuovo fronte:
780 lastre di vetro
1500 lastre di Corian®
25 mila bulloni
250 mila kg di travi in acciaio
Superfici
1800 m2 di pannelli in Corian®
10 mila m2 SLP corpo “F”
Certificazioni e Obiettivi sostenibilità
Credits
In collaborazione con
RTI Castaldo SpA (Main contractor)
SAB – Architettura Ingegneria Integrata
The new 40 million-euro-worth project Nuova Linate aims to restyle image and usability of one of the main Italian airports, with almost 10 million passengers. The building already incorporates the original structure designed in 1934 by Gianluigi Giordani, and modernized with several interventions, including one by Aldo Rossi, in 1991. It was crucial meticulously engineer the project with the objective of ensuring seamless airport operations throughout all stages. A first phase on the main terminal, which involved TEKNE designers in all design phases, included the construction of a new façade and the revamping of the arrivals and baggage claim area. The city airport has now changed its face, updated to a Cerri & Associati architectural project, through the installation of a new glazed canopy on the departures floor and shiny aluminum cladding over the structural elements. The entryways are highlighted with new blue finishes, while the prevalent use of white aluminum and glass, along with new heights that allow natural light to permeate inside, gives the building a cleaner modern look, highlighted by new LED lighting system that defines the linearity of the front with low energy consumption. In addition to the façade, the revamping of arrivals and baggage claim terminal on the ground floor was planned and carried out without interrupting activities. New false ceilings with LED lighting systems have been inserted as continuous strips perpendicular to the passenger flow, without intervening on other systems, when efficient. The revamping also involved flooring, finishes, check-in counters, toilets, retail spaces and fixtures. A preliminary phase concerned the preliminary design of the interventions in the BNCN building and the expansion of the F building.